Quote:
Originally Posted by pimpmaster9000
the ICF takes 12cm reinforced concrete...1m3 concrete, high price, is 60 euros...this means for 1m2 I need approx 8 euros  
the steel crap that goes in this is 70cents per kilo "lose" or 80cents per kilo "tied"...
I am too lazy to work out how much the pool will actually cost...I will laugh at any price they give me and have the cash in my pocket at any given time...
|
Depending on how you want to build it, a 100m2 pool still need a concrete floot, so lets say you go easy and only want 15cm walls, you are at 15 m3 of concrete = 60 * 15 = €900 alone for the concrete.
For steel, you need 500-700kg for the floor alone = uppps the €500 I told you
8 mm dimensions in sections of 2350x5000 mm 150x150 mm masks, is 62.5 kg each
And then comes the ICF.. those are NOT cheap
Then comes the painting or surface treatment
and are you and your slav army gonna dig the hole by hand to keep cost down?
What about around the pool? gonna just let gras or gravel fall into your pool?